![Doreen-Tower1](http://milestonealuminium.com/wp-content/plugins/revslider/public/assets/assets/dummy.png)
![](http://milestonealuminium.com/wp-content/plugins/revslider/public/assets/assets/dummy.png)
![](http://milestonealuminium.com/wp-content/plugins/revslider/public/assets/assets/dummy.png)
![doreen tower](http://milestonealuminium.com/wp-content/plugins/revslider/public/assets/assets/dummy.png)
![](http://milestonealuminium.com/wp-content/plugins/revslider/public/assets/assets/dummy.png)
![Doreen-Tower3](http://milestonealuminium.com/wp-content/plugins/revslider/public/assets/assets/dummy.png)
![](http://milestonealuminium.com/wp-content/plugins/revslider/public/assets/assets/dummy.png)
![Doreen-Tower4](http://milestonealuminium.com/wp-content/plugins/revslider/public/assets/assets/dummy.png)
![Doreen-Tower5](http://milestonealuminium.com/wp-content/plugins/revslider/public/assets/assets/dummy.png)
![Doreen-Tower6](http://milestonealuminium.com/wp-content/plugins/revslider/public/assets/assets/dummy.png)
THE CHALLENGES
It was our first overseas project, we faced challenges in shipments, custom clearances mainly, everything else was executed smoothly.
PROJECT DETAILS
Client: | Doreen Developments Ltd |
Location: | Dhaka, Bangladesh |
Surface Area: | 5800 sqm |
Completed: | 2008 |
Value: | 7 Cr |
Architect: | |
Façade Consultant: | Engineering Design by Milestone |
Scope of work: | 1. Unitised structural glazing |